检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:赵伟娟 ZHAO Wei-juan(Hebei Provincial Communications Planning,Design and Research Institute Co.Ltd.,Shijiazhuang 050000,China)
机构地区:[1]河北省交通规划设计研究院有限公司,石家庄050000
出 处:《工程建设与设计》2025年第3期186-189,共4页Construction & Design for Engineering
摘 要:作为2022年中国冬奥会重大交通保障项目,延庆至崇礼高速公路的松山隧道和翠云山隧道工期紧迫,为了加快施工进度,松山隧道采用迂回导洞方案,翠云山隧道采用施工斜井分岔方案,论文分别分析了这两种方案提出的原因、具体内容以及实施效果。实践结果证明,两种方案极大地加快了施工进度,为工程按期完工奠定了基础。As a major transportation support project for the 2022 Winter Olympics in China,Songshan Tunnel and Cuiyunshan Tunnel from Yanqing to Chongli Expressway are in a tight schedule.In order to speed up the construction progress,Songshan Tunnel adopts the detour guide tunnel scheme and Cuiyunshan tunnel adopts the construction inclined shaft branching scheme.This paper analyzes the reasons,specific contents and implementation effects of these two schemes respectively.The practical results show that the two schemes greatly accelerate the construction progress and lay the foundation for the completion of the project on schedule.The practical results show that the two schemes greatly accelerate the construction progress and lay the foundation for the completion of the project on schedule.
分 类 号:U455.4[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.222