许昌铁矿北进风井冻结法水文孔异常分析  

Analysis of hydrologic hole anomaly by freezing method of north inlet air shaft in Xuchang Iron Mine

在线阅读下载全文

作  者:王龙 WANG Long(Beijing China Coal Mine Engineering Company Li mited,Beijing 100013,China)

机构地区:[1]北京中煤矿山工程有限公司,北京100013

出  处:《建井技术》2025年第1期91-94,71,共5页Mine Construction Technology

摘  要:许昌铁矿北进风井采用了冻结施工技术。由于水文孔施工完成后经历了较长的停工期,导致原有水文孔失效。因此,在十年后重新开工时重新施工了新水文孔,并采取了多项措施以确保新水文孔能够准确反映冻结壁的交圈情况,为未来类似工程提供了宝贵的参考经验。Freezing construction technology has been adopted in the north inlet air shaft of Xuchang Iron Mine.Due to the long downtime after the completion of the hydrologic hole construction,the original hydrologic hole failed.As a result,the new hydrologic hole was re-constructed when work resumed ten years later,and a number of measures were taken to ensure that the new hydrologic hole accurately reflected the intersection of the freezing wall,providing valuable reference experience for similar projects in the future.

关 键 词:立井井筒 冻结法 水文孔 冻胀水计算 水位观测 

分 类 号:TD265.34[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象