银江水电站全水头运行贯流式机组的设计  

Design of Full-head Tubular Set for Yinjiang Hydropower Project

作  者:郭学洋 杨锐 张祝年 GUO Xueyang;YANG Rui;ZHANG Zhunian(Changjiang Survey,Planning,Design and Research Co.,Ltd.,Wuhan Hubei 430010;Panzhihua China Resources Hydropower Development Co.,Ltd.,Panzhihua Sichuan 617067;Sichuan Chuantou Energy Stock Co.,Ltd.,Chengdu Sichuan 610044)

机构地区:[1]长江勘测规划设计研究有限责任公司,湖北武汉430010 [2]攀枝花华润水电开发有限公司,四川攀枝花617067 [3]四川川投能源股份有限公司,四川成都610044

出  处:《四川水力发电》2025年第1期25-30,83,共7页Sichuan Hydropower

摘  要:阐述了银江水电站贯流式机组的选型设计以及对水轮机水力开发方面进行优化设计的过程,最终设计出的机组性能参数达到或优于合同要求,能够适应银江水电站尾水位条件复杂,低水头泄洪等实际运行条件;创新研发出我国单机容量最大、转轮直径最大的全水头运行灯泡贯流式水轮发电机组。This article introduces the process of selecting and designing the tubular unit of Yinjiang Hydropower Project,and optimizing the hydraulic development of the turbine.The performance parameters of the unit finally design meet or exceed the contract requirements,and are suitable for the complex tailwater level conditions and low head flood discharge of Yinjiang Power Project.The bulb tubular turbine generator set with the largest single unit capacity and the largest runner diameter has been developed in China.

关 键 词:银江水电站 全水头 选型 设计 最大灯泡贯流式水轮发电机组 

分 类 号:TV7[水利工程—水利水电工程] TV51TV734.21

 