基于强风化花岗岩地质条件下的钢管桩沉桩施工技术研究  

Research on the Construction Technology of Steel Pipe Pile Sinking based on the Geological Conditions of Strongly Weathered Granite

在线阅读下载全文

作  者:罗钟成 Luo Zhongcheng(NO.3 Engineering of CCCC Guangzhou Dreding Co.Ltd.,Foshan,Guangdong 528231)

机构地区:[1]中交广航局第三工程有限公司,广东佛山528231

出  处:《江西建材》2024年第11期321-323,共3页

摘  要:文中以阳西县城至溪头沿河道路大洲村段桥梁建设工程为例,阐述了工程强风化花岗岩地质条件,结合钢管桩沉桩施工难点,提出了应对钢管桩焊接防腐加工偏差、钢管桩起吊偏差、桩尖端断裂等难题的具体措施,以供参考。The article takes the bridge construction project of Dazhou village on the road from the Yangxi county town to Xitou along the river as an example,briefly explains the geological conditions of strongly weathered granite in the project,and combines the difficulties of steel pipe pile sinking construction to propose construction technology application measures to solve the welding and anti-corrosion processing deviation of steel pipe piles,lifting deviation of steel pipe piles,and pile tip fracture.The construction effect is analyzed to provide reference for relevant workers.

关 键 词:强风化花岗岩 复杂地质 钢管桩沉桩 

分 类 号:TU74[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象