小浪底引黄工程(引水干线部分)7^(#)施工支洞优化方案  

Optimization Scheme for the 7^(#)Construction Adit of the Xiaolangdi Yellow River Diversion Project(Main Water Diversion Line)

在线阅读下载全文

作  者:高利军 GAO Li-jun

机构地区:[1]山西小浪底引黄水务集团有限公司,山西运城043700

出  处:《山西水利科技》2025年第1期21-22,共2页Shanxi Hydrotechnics

摘  要:高埋深、长距离引水隧洞斜井支洞施工十分不便,对主洞施工影响极大,影响工期和混凝土质量,且存在较大安全风险。小浪底引黄工程(引水干线部分)施工Ⅴ标7#施工支洞施工中,对斜井支洞进行了优化,成功地解决了工程进度、质量和安全问题,节省了施工成本。The construction of inclined shaft adit with high burial depth and long-distance water diversion tunnels is very inconvenient,which has a great impact on the construction of the main tunnel,affects the construction period,affects the quality of concrete,and poses significant safety risks.During the construction of the 7#construction support tunnel of Section V of the Xiaolangdi Yellow River Diversion Project(diversion mainline),the inclined shaft adit was optimized,successfully solving the problems of project progress,quality,and safety,and saving construction costs.

关 键 词:支洞优化 方案 小浪底工程 

分 类 号:TV554[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象