包含电动汽车充电站的区域电网优化调度  

Optimal Scheduling for Regional Power Grid Including Electric Vehicle Charging Stations

在线阅读下载全文

作  者:张仕鹏 彭超逸 黄楚鸿 左嘉志 刘明波[1] ZHANG Shipeng;PENG Chaoyi;HUANG Chuhong;ZUO Jiazhi;LIU Mingbo(School of Electric Power Engineering,South China University of Technology,Guangzhou 510640,China;China Energy Engineering Group Guangdong Electric Power Design Institute Co.,Ltd.,Guangzhou 510663,China;Power Dispatching and Control Center,CSG,Guangzhou 510663,China)

机构地区:[1]华南理工大学电力学院,广州510640 [2]中国能源建设集团广东省电力设计研究院有限公司,广州510663 [3]中国南方电网有限责任公司电力调度控制中心,广州510663

出  处:《南方电网技术》2025年第3期51-59,共9页Southern Power System Technology

基  金:国家自然科学基金资助项目(52077083,U1911401)。

摘  要:区域电网优化调度是提高可再生能源消纳水平、提升电力系统可靠性、降低运行成本的重要手段。为此,针对包含电动汽车(electric vehicle,EV)充电站的区域电网提出了基于拍卖的两阶段优化调度方式。第一阶段根据本地可再生能源发电和用电的预测值对区域电网进行日前调度。第二阶段根据发电和用电的实际测量值对日前调度结果进行二次调整。针对第二阶段设计电能拍卖方法,利用EV的充放电能实现区域电网的实时供需平衡,并证明所提的拍卖方法具有激励相容性质,保证EV在拍卖中提交真实的电能需求或供给信息。仿真结果表明所提的两阶段方法能够降低区域电网的运行成本,并使得EV只有在提交真实信息的情况下才能获得最高的效用。Optimal scheduling for regional power grid is an important means to increase the consumption of renewable energy,enhance the reliability of power systems,and reduce operating costs.Therefore,focusing on a regional power grid including electric vehicle(EV)charging stations,an auction-based two-stage optimal scheduling method is proposed.In the first stage,the regional power grid is scheduled one day ahead based on the predicted values of local renewable energy generation and consumption.In the second stage,the day-ahead scheduling results are adjusted according to the actual measured values of generation and consumption.For the second stage,an electricity auction method is designed to achieve real-time supply-demand balance of the regional power grid by using EV charging and discharging energies.It is proved that the proposed auction method has the property of incentive compatibility,which ensures that EVs submit true energy demand or supply information in the auction.Simulation results show that the proposed two-stage method can reduce the operating cost of the regional power grid and make EVs obtain the highest utilities only when true information is submitted.

关 键 词:电力调度 区域电网 充电站 电动汽车 

分 类 号:TM732[电气工程—电力系统及自动化]

 