斜拉索临时支撑的非对称单塔斜拉桥无应力索长研究  

Research on Stress Free Cable Length of Asymmetric Single Tower Cable-stayed Bridge with Temporary Support of Cable-stayed Cables

在线阅读下载全文

作  者:闫武 高启战 YAN Wu;GAO Qizhan(China Communications First Engineering Bureau Group Co.,Ltd.,Beijing 100101,China)

机构地区:[1]中交一公局集团有限公司,北京100101

出  处:《粉煤灰综合利用》2025年第2期138-143,共6页Fly Ash Comprehensive Utilization

摘  要:以永定河特大桥为研究对象,采用Midas/Civil软件建立桥梁有限元仿真模型,对桥体的无支架工艺施工过程完成模拟和计算分析。通过对比有限元法计算结果和监测数据,研究斜拉索临时支撑施工方法对模型斜拉索的索力、无应力索长以及桥梁线形和内力的影响规律。结果表明:在多次张拉后,索力仍然达到了理想效果,并且桥梁线型和应力的变化均受到索力的影响,且最终成桥时的实测数据与设计值相符,保证桥梁的施工和运营过程中能够更加安全高效。Taking the Yongding River Grand Bridge as the research object,establish a finite element simulation model of the bridge using Midas/Civil software,and complete the simulation and calculation analysis of the unsupported construction process of the bridge body.By comparing the results of finite element method calculations and monitoring data,this study investigates the influence of temporary support construction methods on the cable force,unstressed cable length,bridge shape,and internal forces of the model cable.The results showed that after multiple stretches,the cable force still achieved the desired effect,and the changes in bridge shape and stress were affected by the cable force.The measured data at the final completion of the bridge matched the design values,ensuring that the construction and operation of the bridge could be safer and more efficient.

关 键 词:斜拉桥 模拟分析 无支架安装 多次张拉 

分 类 号:U448.27[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象