检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:付小烦[1] 师少辉[1] FU Xiao-fan;SHI Shao-hui(CCCC Second Highway Consultants Co.Ltd.,Wuhan 430056,China)
机构地区:[1]中交第二公路勘察设计研究院有限公司,武汉市430056
出 处:《公路》2025年第4期182-187,共6页Highway
摘 要:英德市省道S292延长线一级公路新建工程北江四桥跨堤引桥为单跨102m预制拼装简支梁桥,全桥分为两幅,单幅桥宽18.25m。主梁采用R120级UHPC,纵向预应力采用钢绞线成品索体外预应力形式,张拉控制应力1209MPa,按全预应力构件设计。主梁采用双箱单室等截面箱梁,高度为4m,箱室间通过UHPC现浇湿接缝将两个箱室连接形成整体。标准节段长4m,单片箱梁共分为25个节段。节段预制采用长线法,经高温蒸养后,在支架上进行拼装。节段预制时,采用添加冰块及布置冷却水管等方式控制水化热。The Beijiang No.4 Bridge,a new highway construction project of the S292 extension line of Yingde provincial highway,is a prefabricated simply supported beam bridge with a single span of 102 m.The bridge is composed of two separated bridges with a single bridge width of 18.25 m.The main girder adopts UHPC R120,which is a longitudinal prestressed structure.The external prestressing form of steel strand finished cable is adopted,the tension control stress is 12o9 MPa,which is designed according to the full prestressed component.The main girder adopts double-box single-room box girder with equal section,and the height is 4 m.The box cells are connected to form a whole through the UHPC cast-in-place wet joint.The standard segment is 4 m long,and the single box girder is divided into 25 segments.The segment is prefabricated by long-line method.After high temperature steam curing,the bracket is assembled.During segmental precasting,the hydration heat is controlled by adding ice blocks and arranging cooling water pipes.This bridge is the largest span UHPC simply supported beam bridge built in China up to date.
关 键 词:桥梁工程 大跨简支梁 超高性能混凝土(UHPC) 节段预制拼装 长线法 大体积
分 类 号:U448.21[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.49