机构地区:[1]中南大学,湖南长沙410083
出 处:《矿业研究与开发》2002年第6期19-20,40,共3页Mining Research and Development
摘 要:水口山铅锌矿鸭公塘老采区在实施闭坑工程中,需在与老鸦巢区相连接的4个中段建4座防水闸,以隔断两区的水流通道,保证安全生产。文章阐述了防水闸有关设计参数的选取、闸体有关数据的设计计算,以及为防渗所采用的普通注浆和双液注浆技术。完成施工后,经过近两年的实践检验,堵水效果显著,获直接经济效益300余万元。In the workings closing project of the Yagongtang old mined-out area in Shuikoushan Lead Zinc Mine, four water-proofing gates were to be constructed at the four levels which connect the Yagongtang old mined-out area with the old Yachao area, so as to cut the water channel connecting the two areas and guarantee the working safety. This paper deals with selection, design and calculation of the parameters for the water-proofing gates, and describes the conventional grouting and double-liquid grouting technologies adopted in the project for anti-leaking. The water-proofing performance of the project proved excellent for the past two years ever since its commission, with a direct economic gain of over 3 million yuan.
分 类 号:TD745.25[矿业工程—矿井通风与安全]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.31