机构地区:[1]长江科学院,湖北武汉430010
出 处:《水电站设计》2003年第1期64-69,102,共7页Design of Hydroelectric Power Station
摘 要:叙述了国内外河道高落差截流工程的进展情况。在龙口进占中,根据抛投块体的稳定理论对水力参数的计算可找到截流的困难段。立堵截流在运用伊兹巴什公式计算中,式中的稳定系数K考虑了戗堤端头坡度、河床底面糙度、石块、混凝土块以及单体、串体的影响。在减轻高落差截流难度方面,可通过对龙口范围采用石渣料、拦石坎、预抛填底保护,以及拦石栅辅以多戗、平堵等解决。并列举了典型工程实例。Development of high drop river closure work in China and abroad is elaborated in this paper.During closing closure gap,difficult closure section can be found out by hydraulic parameters calculation based on stability theory of dumped blocks.In the formula offered by С.В.Изъащ,influences of closure dike end slope,roughness of river bed,rock blocks,concrete blocks and chain linked blocks are considered in determining the stability coefficient K.In order to reduce difficulties in high drop river closure,in the closure gap rock blocks,rock detaining sill,predumped bed protection blocks,rock detaining grid,multiple closure dikes and horizontal closure can be used.Typical projects as examples are also listed in the paper.
分 类 号:TV551.2[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.17.164.81