三峡工程三期RCC围堰工程  被引量:1

Phase III RCC Cofferdam Construction of TGP

在线阅读下载全文

作  者:张曙光[1] 

机构地区:[1]中国长江三峡工程开发总公司,湖北宜昌443002

出  处:《中国工程科学》2003年第11期79-81,共3页Strategic Study of CAE

摘  要:三期RCC围堰工程项目是确保三峡工程 2 0 0 3年蓄水、通航和发电目标按期实现的关键项目 ,也是右岸厂房坝段和右岸电站厂房等后续施工项目安全施工的保障。受施工通航、施工场地及工期条件等限制 ,三期RCC围堰的混凝土施工强度和上升高度均超过目前现有施工水平 ,针对这些难点开发出有效的处理工艺 。The phase III RCC cofferdam construction belongs to the phase III di version works. It is a key item to ensure achievement of the reservoir impoundme nt, navigation and power generation in 2003 and the guarantee to the safety cons truction of the follow-up right-bank intake dam section and the powerhouse. Re st rained by navigation while construction, the construction site and duration, bo th the con creting in tensity and the rise height of the phase III RCC cofferdam exceed the current co nstruction level. In view of these difficulties, a huge amount of research work has been performed by relevant departments and is described in the paper.

关 键 词:三峡工程 RCC围堰 混凝土 

分 类 号:TV551.3[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象