钢筋混凝土框架楼群定向爆破拆除  被引量:4

Demolition of a Group of Reinforced Concrete Frame Buildings by Blasting

在线阅读下载全文

作  者:张翠兵[1] 邓志勇[2] 张志毅[1] 刘慧[1] 

机构地区:[1]铁道科学研究院铁道建筑研究所,北京100081 [2]北京科技大学土木与环境学院,北京100083

出  处:《中国铁道科学》2004年第1期110-114,共5页China Railway Science

摘  要:介绍采用一次爆破拆除3栋钢筋混凝土框架楼房的设计原则、爆破参数及安全防护措施。由于被拆楼群周围环境复杂,1#楼沿楼体纵向采用自东向西逐段坍塌方式拆除,为2#楼的向南倒塌预留出空间,3#楼最后向南倾倒。详细介绍1#楼所采用的爆破方案及实施过程。在爆前预先切割横梁把楼体分割成相互独立的四部分,利用秒差雷管分别依次从东向西逐段进行爆破和解体。着重介绍了爆破切口高度的确定方法、钻孔爆破参数的选取原则、试爆方案的实施、起爆顺序的确定、预处理方法以及相应的安全防护措施等。A group of three reinforced concrete frame buildings was demolished by blasting with one initiation and collapsed in designed direction. The situation around the demolished buildings is very complicated. The one-direction section-by-section collapsing scheme is used to demolish building No. 1. Thus it saves space for building No. 2 to be disintegrated in the south direction and building No. 3 too. The paper depicts the blasting solution and execution procedure of demolishing building No. 1. Before blowing building No. 1, the cross beam of building No. 1 is cut into four independent parts. And second-detonators are used to blast the building from east to west. The paper focuses on the defined method of the blasting cut height, the selection rationale of drill and blasting parameters, the execution of the trial-blasting solution, the prime sequence, the pre-treatment method and the corresponding safety precautions.

关 键 词:爆破拆除 楼群爆破 定向爆破 钢筋混凝土框架 施工方法 

分 类 号:TU746.5[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象