机构地区:[1]华东电力设计院有限公司,上海 [2]国网(嘉兴)综合能源服务有限公司,浙江 嘉兴
出 处:《土木工程》2021年第6期606-614,共9页Hans Journal of Civil Engineering
摘 要:基于某城区电缆隧道工程,采用有限元模型模拟了隧道开挖施工的全过程,对施工过程中周边已有建构筑物及电缆隧道本身的位移变形趋势均进行了计算分析。结果表明,电缆隧道侧穿已有建构筑物时,已有结构主要发生向下的沉降变形和靠近隧道的水平位移,针对变形趋势建议采用相应地面注浆加固以及增加同步注浆和二次注浆量的措施来保证工程的安全推进。Based on the cable tunnel project in a city, the whole process of tunnel excavation is simulated by using finite element model. The displacement and deformation trend of existing buildings and cable tunnels around the construction process are calculated and analyzed. The results show that when the cable tunnel side passes through the existing buildings, the existing structure mainly undergoes downward settlement deformation and horizontal displacement towards the tunnel. According to the deformation trend, it is suggested to adopt corresponding ground grouting reinforcement and increase synchronous grouting and secondary grouting to ensure the safety of the project.
分 类 号:U45[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.200