作 者:谢后客
机构地区:[1]保利长大工程有限公司,广东 广州
出 处:《土木工程》2023年第5期707-712,共6页Hans Journal of Civil Engineering
摘 要:在双峰寨隧道施工过程中,部分施工区域存在围岩稳定性较差、纵向坡率大和洞内涌水等施工难题。基于施工过程中的难点,在隧道暗洞浅埋段和洞口分别采用超前大管棚配备超前注浆小导管和Vc型复合式衬砌;在纵向坡率较大地段采取了反坡排水的施工方案。测量结果表明:采用了反坡排水后,最终将排水累积量控制在了100 m3/h左右;依托于各难点处采用的施工方案,隧道洞口的监测沉降值约为47 mm,沉降值在接受范围内。During the construction of Shuangfengzhai Tunnel, there are construction problems in some construction areas, such as poor stability of surrounding rock, large longitudinal slope rate and water inrush in the cave. Based on the difficulties in the construction process, the shallowly buried section of the tunnel and the entrance of the tunnel are equipped with advanced grouting small conduit and Vc-type composite lining. In the section with a large longitudinal slope, a construction plan of reverse slope drainage was adopted. The measurement results show that after using reverse slope drainage, the cumulative amount of drainage is finally controlled at about 100 m3/h. Relying on the construction scheme adopted at each difficult point, the monitoring settlement value of the tunnel entrance is about 47 mm, and the settlement value is within the acceptable range.
分 类 号:U45[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.31