机构地区:[1]同济大学土木工程学院水利工程系,上海 [2]中建港航局集团有限公司,上海
出 处:《土木工程》2024年第4期383-388,共6页Hans Journal of Civil Engineering
摘 要:通过高桩梁板码头结构数值模拟与分析,探讨了开挖过程中土体卸荷对高桩码头群桩的影响。使用PLAXIS-3D有限元软件构建了三维模型,考虑了地基土层、开挖工况、桩基布置方式的影响并通过模拟分析了不同阶段的桩基结构弯矩、位移等关键参数。研究表明:发现随着开挖深度增加,桩身水平位移和沉降量增加,并与开挖深度呈线性关系。同时,开挖过程会导致码头桩基产生明显弯矩,呈现“弓”字形变化。Through numerical simulation and analysis of high-piled wharf structures, the influence of soil unloading during excavation on the piles of high-piled wharves was investigated. A three-dimensional model was constructed using PLAXIS-3D finite element software, considering the effects of foundation soil layers, excavation processes, and pile layout methods. Key parameters such as bending moment and displacement of pile foundations at different stages were analyzed through simulation. The study revealed that with increasing excavation depth, horizontal displacement and settlement of the piles increased linearly. Additionally, excavation processes led to significant bending moments in the wharf piles, exhibiting a “bow” shaped variation.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15