关于山区河流码头施工水位的讨论  被引量:4

On the Construction Water Level of Wharf in Mountainous Rivers

在线阅读下载全文

作  者:温焰清[1] 王多垠[1] 宋成涛[1] 黄然[1] 

机构地区:[1]重庆交通大学河海学院,重庆400074

出  处:《重庆交通大学学报(自然科学版)》2010年第6期969-971,991,共4页Journal of Chongqing Jiaotong University(Natural Science)

基  金:重庆市重大科技专项基金项目(CSTC;2009AA6029)

摘  要:三峡成库后,经验取值的方法不再适用于内河山区河流码头建设的施工水位确定。以寸滩码头为例,分析了码头所在河段天然情况下历年各月平均水位、成库后各月水位后,得出可连续施工天数;结合工程量,将其与预计施工工期对比,再视特殊具体洪水情况,作出调整。该方法较传统经验取值法更为准确、合理,对施工质量及经济效益等方面都有积极作用。After the Three Gorges Reservoir was built,the experience value could not be applied to determining construction levels of inland mountainous river.After taking Cuntan Wharf as an example,the monthly average water level and water level after the completion of each month in natural situation were analyzed and the number of days of continuous construction was obtained.The said number was compared to the estimated construction period based on engineering quantity;adjustments were made according to specific flood of special circumstances.Compared to traditional method of experience,the present one was more accurate and reasonable and it could play a positive role in improving construction quality and reducing costs.

关 键 词:山区河流码头 寸滩 施工水位 

分 类 号:U656.1[交通运输工程—港口、海岸及近海工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象