摘  要:介绍了湖南镇水电站#5机组减振增容技术改造的原因,论述了#5机组减振增容技术改造的实施情况。湖南镇水电站#5机组改造后的试验和运行结果表明,湖南镇水电站#5机组减振增容技术改造非常成功,机组的技术指标达到了增容改造的预期效果。The reasons of reformation of unit No.5 in Hunanzhen Hydropower Station for vibration attenuation and capacity expansion were introduced.The implementation of the reformation for vibration attenuation and capacity expansion of unit No.5 was expounded.The test and operation results of reformed unit No.5 of Hunanzheng Hydropower Station show that the reformation is very successful;and the technical data of the unit were reached expected value of the capacity expansion reformation.

关 键 词:水轮发电机组 减振 增容 技术改造 

分 类 号:O328[理学—一般力学与力学基础] TK73[理学—力学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象