隧道浅埋、露顶地段反压回填暗挖施工技术  被引量:4

Construction Technology of Back Pressure Backfilling and Underground Excavation in Shallow-Buried and Top-Exposed Section of Tunnel

在线阅读下载全文

作  者:李晋峰[1] 夏龙[1] 

机构地区:[1]中铁一局集团第五工程有限公司,宝鸡721006

出  处:《北方交通》2012年第8期92-95,共4页Northern Communications

摘  要:凤凰山隧道在距进口210~250m处与沟壑平交,导致洞身21m浅埋17m拱顶外露,通过对三种施工方法的比选确定采用10%水泥稳定碎石反压回填,在地表注浆固化形成壳体后实施暗挖。施工实践证明该方法合理有效,故对其施工技术和工艺要求进行总结,为类似工程提供参考或借鉴。The Phoenix Hill Tunnel crosses with gully parallelly from 210 -250m of the entrance, which leads to 21m of the cave body shallow buried,and 17m of arch top exposed. Through the comparison and selection among three construction methods, 10% cement stabilized macadam back pressure backfilling method is adopted, and underground excavation is implemented after shell forming through grouting and curing of the earth surface. The con- struction practice shows that this method is reasonable and effective, so its construction technology and technological requirement are summarized, thus providing references for similar projects.

关 键 词:浅埋 露顶 反压回填 地表注浆 暗挖 明洞暗作 

分 类 号:U455[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象