机构地区:[1]广州轨道交通建设监理有限公司,广州510010 [2]广州市地下铁道总公司,广州510030
出 处:《都市快轨交通》2012年第4期74-77,共4页Urban Rapid Rail Transit
摘 要:盾构机通过中间风井的一般方式是:先完成全部中间风井主体结构,洞门处地下连续墙钢筋混凝土结构,而后盾构机过站,指出这相当于完成一次到站、平移、再次始发的过程,造成涌水涌砂风险集中。随后介绍一种工法:临时回填风井底板结构,盾构从回填土中穿越,最后开挖并修筑中间风井结构,以此降低盾构过风井的涌水涌砂风险。Normally for a shield to pass through a ventilation shaft,the body structure of the shaft should be completed at first,then holes are bored out on the reinforced concrete walls of the shaft,and the shield passes through the shaft.The process includes the arrival of the shield,horizontal shift of it,and departure of the shield and in the process there exist the risks of water gushing and soil gushing.Authors introduced a technology to reduce the risks: first,backfill the bottom structure of the shaft,then have the shield pass through the backfilling,and finally excavate the backfilling and construct the shaft.
分 类 号:U455[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.117