作 者:罗琼[1]
机构地区:[1]中铁上海设计院集团有限公司,上海200070
出 处:《路基工程》2013年第5期148-151,共4页Subgrade Engineering
摘 要:以广州地铁14号线的工程为例,对地铁高架桥与地下隧道衔接处路基过渡段设计进行研究,论证了路基过渡段的结构形式、填料设计、整体道床地基加固处理比选等,并对过渡段路基的工后沉降、CFG桩承载力进行检算,均满足规范要求。Taking Guangzhou Metro Line 14 project as the example, this paper explored the design of transition section at the junction of the viaduct and the underground tunnel on the metro line to the extent that the structure form, filling design, and the comparison and selection of the roadbed foundation reinforcement of this transition section were demonstrated; moreover, the post-construction settlement of the subgrade thereof and the bearing capacity of CFG pile were calculated, all of which meet the standard requirements.