基于几种浮置板结构施工工法的对比研究  被引量:4

Comparison of Construction Methods with Several Kinds of Floating Slab Track Structure

在线阅读下载全文

作  者:曲腾飞[1] 王媛[2] 

机构地区:[1]天津市地下铁道集团有限公司,天津300051 [2]天津渤海职业技术学院,天津300402

出  处:《都市快轨交通》2015年第1期110-113,共4页Urban Rapid Rail Transit

摘  要:针对在浮置板轨道结构的施工过程中合理有效地选择施工工法这一难题,重点介绍并对比分析散铺法、预制钢筋笼法、全预制短板浮置板施工和半预制短板浮置板施工这4种浮置板轨道结构的施工工法,通过分析对比得出,半预制短板浮置板施工方法较其他施工工艺简单,适应能力强,施工周期短,施工成本低,特别适合浮置板轨道快速施工。With floating slab track structures being widely used ha urban rai/transit, more and more construction methods appear. How to choose a reasonable and effective construction method in the construction process of floating slab track structure becomes a big problem to engineers. This paper introduces and analyzes the spread method, precast reinforced cage method, whole precast short floating slab construction method and the half floating slab precast short construction method. A contrastive analysis is made among these four floating slab track structures and it is found that floating slab precast short construction method is simpler and more adaptable and requires shorter construction period and lower construction cost. it is especially suitable for rapid construction of floating slab track (FST).

关 键 词:浮置板轨道 轨道结构 施工工法 对比分析 

分 类 号:U213.2[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象