江海直达航道桥索塔浮吊提升转体工艺设计  

Lifting and Swiveling Process Design with Floating Crane for the Tower of River-sea Direct Channel Bridge

在线阅读下载全文

作  者:王紫超[1,2] 牛照[1,2] 陈鸣[1,2] 

机构地区:[1]中交第二航务工程局有限公司,湖北武汉430040 [2]交通部长大桥梁建设施工技术交通行业重点实验室,湖北武汉430040

出  处:《施工技术》2016年第11期24-27,共4页Construction Technology

摘  要:研究了一种桥梁钢塔浮吊提升转体工艺,即由工厂拼装成整体,船运至施工现场,然后通过大型浮吊转体吊装,最后利用导向及精调位装置进行匹配。分析了转体吊装过程中可能遇到的各种问题,并对应提出了具体的、行之有效的解决措施。对转体吊耳、转动铰、滑移系统以及导向调位装置进行了深入研究,并进行了详细设计,各结构新颖,可拆装性好,对钢塔损伤较小,承载能力强。最后对转体吊装及精确调位过程中钢塔的稳定性进行了系统分析,证明了整个过程安全可行。This paper researches a kind of lifting and swiveling technology to the steel tower with floating crane: it was assembled in the factory,transported to the construction site by vessels,then swiveled and hoisted by a floating crane,matching using guide and refined adjustment device at last. The various kinds of problems occurring in the process are analyzed and the effectively specific solutions are proposed. The further study to swivel lifting lugs,rotating hinge,slip system,guiding and adjustable device is carried out as well as detailed design. The structure is original and removable,which is limited damage to steel tower with high bearing capacity. Finally,systematic analysis of the steel tower stability is conducted,which proves the feasibility and safety of the process.

关 键 词:桥梁工程 索塔 转体 浮吊 稳定性 设计 

分 类 号:U445.465[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象