四轨三线制TBM同步衬砌施工有轨运输组织研究  被引量:6

Rail Haulage Organization of Synchronous Lining Construction with TBM Method Under Four Railed Three-wire System

在线阅读下载全文

作  者:薛永庆[1] Xue Yongqing(China Railway 18th Bureau Group Tunnel Engineering Co.Ltd.,Chongqing 400700,China)

机构地区:[1]中铁十八局集团隧道工程有限公司,重庆400700

出  处:《铁道建筑技术》2017年第9期54-57,共4页Railway Construction Technology

基  金:中国铁建股份有限公司科技研究开发计划项目(14-C27)

摘  要:结合引汉济渭岭北工程TBM施工段同步衬砌施工实例,介绍了在TBM法施工的隧洞中,采用四轨三线制轨道模式下,通过优化轨道运行线路及合理使用浮动道岔,实现在不影响TBM正常掘进的情况下,如何有效组织衬砌混凝土的快速运输、浇筑施工同时保证其他来往有轨运输机车编组的通行畅通,实现真正意义上的TBM掘进与二次衬砌同步施工,为今后同类项目的施工提供借鉴。Combined with the synchronous lining construction example of TBM construction section in the water diversion from Hanjiang to Weihe River Project,this paper is based on optimizing rail operating circuit and reasonably using floated turnout in constructing tunnel by TBM under four railed three-wire system,it makes an introduction on how to effectively or-ganize the fast transportation and pouring construction of lining concrete while ensuring the unimpeded pass of other railcars without affecting the normal tunnelling of TBM.As a result,the real synchronous construction in conjunction with TBM tun-nelling and secondary lining is realized,which could provide a reference for construction of similar projects in future.

关 键 词:四轨三线 同步衬砌 有轨运输 

分 类 号:U455.43[建筑科学—桥梁与隧道工程] U455.2[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象