西安南京铁路东秦岭特长隧道设计方案的研究  被引量:3

A Study on Design Program of East Qinling Super-long Tunnel of Xi'an-Nanjing Railway

在线阅读下载全文

作  者:靳宝成[1] 杨国柱[1] 王永安[1] 

机构地区:[1]铁道第一勘察设计院,甘肃兰州730000

出  处:《铁道标准设计》2002年第11期6-9,共4页Railway Standard Design

摘  要:西安南京铁路东秦岭特长隧道全长 12 2 6 8m ,设计为双线加平行导坑方案 ,钻爆法施工。隧道进出口各 35m采用模筑混凝土衬砌 ,洞身其余地段采用复合式衬砌 ,支护均以喷、锚、网为主 ,并辅以钢架。隧道设计总工期为 5 8.32个月 ,是全线的控制性工程。从地质特征、方案比选。East Qinling Super-long Tunnel has a total length of 12,268m. According to design, the twin-track tunnel with parallel heading shall be excavated using drill and blast method. Form concrete lining shall be applied to the sections 35m to entrance and exit, and composite lining shall be applied to the remaining part. Shotcreting, anchor bolts and wire mesh are principal supporting means assisted with steel frame. The tunnel is the control project of Xi'an-Nanjing Railway, and is scheduled to be completed in 58.32 months. Design program of the tunnel is illustrated from geological characteristics, selection of program, and structural design, etc.

关 键 词:东秦岭特长隧道 设计方案 铁路隧道 双线隧道 地质特征 正洞 平行导坑 结构设计 

分 类 号:U459.1[建筑科学—桥梁与隧道工程] U452.[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象