钢垫梁架空维护高铁线路期间提高列车限速的研究  被引量:2

Research on Improvement of Train Speed Limit During Temporary Support Maintenance of High Speed Railway Using Steel Cushion Beam

在线阅读下载全文

作  者:郭宇良 孙军 刘晓光 赵欣欣 杨全亮 GUO Yuliang;SUN Jun;LIU Xiaoguang;ZHAO Xinxin;YANG Quanliang(Postgraduate Department,China Academy of Railway Sciences,Beijing 100081,China;National Railway Track Test Center,China Academy of Railway Sciences Corporation Limited,Beijing 100015,China;Railway Engineering Research Institute,China Academy of Railway Sciences Corporation Limited,Beijing 100081,China;State Key Laboratory for Track Technology of High-speed Railway,China Academy of Railway Sciences Corporation Limited,Beijing 100081,China;CHINA RAILWAY,Beijing 100844,China)

机构地区:[1]中国铁道科学研究院研究生部,北京100081 [2]中国铁道科学研究院集团有限公司国家铁道试验中心,北京100015 [3]中国铁道科学研究院集团有限公司铁道建筑研究所,北京100081 [4]中国铁道科学研究院集团有限公司,高速铁路轨道技术国家重点实验室,北京100081 [5]中国国家铁路集团有限公司,北京100844

出  处:《铁道建筑》2022年第4期86-89,共4页Railway Engineering

基  金:中国国家铁路集团有限公司科技研究开发计划(N2020G041)。

摘  要:针对我国铁路钢垫梁架空维护期间列车限速低(45 km/h)的问题,研究采用新型架空技术将限速提高。为了提高安装效率将钢垫梁原有6根横梁减少2根。通过静力仿真和静载试验,新型钢垫梁位移和应力均满足规范要求。通过多体动力学仿真分析,列车以80 km/h的速度通过时新型钢垫梁的位移、列车的动力学性能指标均满足规范要求;列车以120 km/h的速度通过时新型钢垫梁的位移和列车的脱轨系数、车体加速度、平稳性指标均满足规范要求,但轮重减载率超出限值。因此,建议高速铁路钢垫梁架空维护期间列车限速由45 km/h提高到80 km/h。Aiming at the problem of low train speed limit(45 km/h)during temporary support maintenance of railway steel cushion beam in China,a new temporary support technology was studied to improve the speed limit.In order to improve the installation efficiency,the original six beams of the steel cushion beam are reduced by two.Through static simulation and static load test,the displacement and stress of the new steel cushion beam meet the requirements of the code.Through the multi-body dynamics simulation analysis,when the train passes at the speed of 80 km/h,the displacement of the new steel cushion beam and the dynamic performance index of the train meet the code requirements.When the train passes at the speed of 120 km/h,the displacement of the new steel cushion beam,the derailment coefficient,vehicle-body acceleration and stability index of the train meet the code requirements,but the wheel load reduction rate exceeds the limit.Therefore,it is suggested that the train speed limit be raised from 45 km/h to 80 km/h during temporary support maintenance of high speed railway using steel cushion beam.

关 键 词:高速铁路 架空技术 理论分析 钢垫梁 无砟轨道 静载试验 线路养护维修 列车限速 

分 类 号:U216.4[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象