大直径盾构淤泥地层预加固处理与掘进控制研究  

STUDY ON PRE REINFORCEMENT TREATMENT AND TUNNELING CONTROL OF SILT STRATUM OF LARGE DIAMETER SHIELD

在线阅读下载全文

作  者:周艳家 Zhou Yan-jia

机构地区:[1]中铁电气化局集团有限公司,北京100069

出  处:《建筑技术开发》2022年第16期125-128,共4页Building Technology Development

摘  要:大盾构在低承载力的淤泥质地层掘进过程中,由于盾构头重脚轻,拼装管片过程中盾构机易发生栽头和下沉现象,导致成型隧道线形超限。重点对淤泥地层预加固处理及掘进控制进一步阐述,解决盾构栽头现象和管片上浮问题,以此为类似工程提供参考。In the process of large shield tunneling in muddy stratum with low bearing capacity, due to the light weight of the shield head, the shield machine is prone to topple and sink in the process of segment assembly,resulting in the overrun of the formed tunnel alignment. This paper focuses on the pre reinforcement treatment and tunneling control of muddy stratum, so as to solve the problems of shield heading and segment floating, so as to provide reference for similar projects.

关 键 词:大盾构 淤泥地层 掘进控制 预加固 静压注浆 

分 类 号:U455.3[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象