作 者:张晓晨 ZHANG Xiao-chen(Fujian Luoyuan Minguang Iron and Steel Co.,Ltd.,Luoyuan,Fujian 350600,China)
机构地区:[1]福建罗源闽光钢铁有限公司,福建罗源350600
出 处:《云南冶金》2024年第1期145-150,共6页Yunnan Metallurgy
摘 要:针对120 t炼钢转炉更换炉衬、煤气公共管道检修,会导致系统全停、影响产能的问题,采取了相应措施:休风前1#、2#高炉调节,包括渣、铁及产量调节;休风期焦炭、炉温、炉渣二元碱度及上休风料调节;复风前准备,1#、2#高炉复风及恢复炉况等操作。采取措施释放产能后3 d内恢复至检修前水平,实现炉况稳定及快速达产目标。Furnace lining replacement,and gas public pipeline overhauling of 120 t steelmaking converter can lead to a complete shutdown of the system,and affect the production capacity,so the following corresponding measures were taken:1#,2#blast furnace conditioning before blowing-down,including regulation of slag,iron and yield;regulation of coke,furnace temperature,binary basicity of furnace slag,and regulation of blowing-down materials;preparation before reblowing,reblowing of 1#,2#blast furnace,and recovering of furnace operation.After 3 days of the above-mentioned measures were taken,the yield was recovered to the levels before overhauling,it realized the stability of furnace conditions and the aim of rapidly reaching the target output.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.144.252.197