检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:李存良 李鹏飞 王锴 张毅毅 王浩 LI Cunliang;LI Pengfei;WANG Kai;ZHANG Yiyi;WANG Hao(Shaanxi Construction Engineering Holding Group Future City Innovation Technology Co.,Ltd.,Xi′an 712000,China;Shaanxi Construction Engineering Group Co.,Ltd.,Xi′an 710003,China;SCEGC Mechanized Construction Co.,Ltd.,Xi′an 710032,China)
机构地区:[1]陕西建工控股集团未来城市创新科技有限公司,陕西西安712000 [2]陕西建工集团股份有限公司,陕西西安710003 [3]陕西建工机械施工集团有限公司,陕西西安710032
出 处:《桥梁建设》2024年第5期156-162,共7页Bridge Construction
基 金:陕西省交通运输厅2023年度交通科研项目(23-49K)。
摘 要:西安地铁10号线渭河特大桥主桥为主跨300 m的曲线上加劲连续钢桁梁桥,采用公轨合建,双层桥面布置,上部结构采用超大型钢桁梁与曲线加劲弦组合结构。主桥施工时先架设钢桁梁,再施工刚性加劲弦。钢桁梁采用步履式顶推+滑块滑移施工,顶推采用南、北双向同步施工。为保证顶推施工过程中主体结构及临时支撑结构的受力安全,采用MIDAS Gen软件建立主桥有限元模型,采用生死单元法进行施工全过程分析,对钢桁梁承载力、支座反力、合龙阶段落梁变形调整值、合龙阶段温度效应影响、顶推过程中不同步的影响以及瞬时阵风作用下顶推体系承载力进行分析验算。结果表明:钢桁梁的承载力及瞬时阵风作用下顶推体系承载力均满足规范要求;钢桁梁顶推时墩顶最大支座反力取值24000 kN;南侧W05墩与北侧L08临时墩落梁变形调整值分别取-60 mm和-40 mm,以消除合龙口端部下挠变形;以环境温度20℃为参考值,整体升温不超过10℃和上、下弦温度梯度为10℃以内时对合龙影响不大;顶推过程中横、纵向瞬时不同步位移建议分别控制在5 mm和20 mm以内。The main bridge of Weihe River Bridge carrying a section of the Xi′an Metro Line 10 is a bridge with superstructure consisting of extra-large steel trusses,stiffened by two continuous spans of upper arch chords and inclined rigid suspenders.The bridge has two levels of decks accommodating road and light rail traffic,respectively.During the construction,the steel trusses were erected ahead of the stiffening upper arch chords.The steel trusses were erected by a crawler-type incremental launching system from the north and south banks towards the center,assisted by sliders.The construction process of the full bridge was numerically simulated in MIDAS Gen to ensure the loading safety of the main bridge structure and the temporary supporting structures by activating and deactivating elements during analysis.Multiple factors were analyzed and checked,including the load bearing behaviors of steel trusses,reaction forces of bearings,truss lowering deformation adjustment at closing stage,thermal effects at closing stage,asymmetry in incremental launching,and the loading bearing capacity of the incremental launching system under gusts.It is shown that the load bearing capacity of the steel truss girder bridge and the load bearing capacity of the incremental launching system met the code requirements.The maximum reaction force of bearings at each pier was 24000 kN.The truss lowering deformation adjusting values for the south W05 pier and the north L08 temporary pier were-60 mm and-40 mm,respectively,aiming to eradicate the down warping of tips of cantilevers at the closure gap.The closing of the superstructure would not be hindered,as the integral temperature rise is less than 10℃,considering a reference ambient temperature at 20℃,and the temperature gradients of the upper and lower chords are within 10℃.The transverse and longitudinal instantaneous asymmetric displacements during incremental launching were controlled within the ranges of 5 mm and 20 mm,respectively.
关 键 词:公轨两用桥 钢桁梁 步履式顶推 滑块滑移 施工阶段 受力分析 有限元法
分 类 号:U448.12[建筑科学—桥梁与隧道工程] U445.462[交通运输工程—道路与铁道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.7