铁路隧道竖井施工设备拆解下放组装定额测定与研究  被引量:2

Determination and Research on Dismantling,Lowering and Assembling Quota of Railway Tunnel Shaft Construction Equipment

在线阅读下载全文

作  者:徐伟 吴炜 张恒辉 XU Wei;WU Wei;ZHANG Henghui(China Railway Tunnel Group CO..LTD,Guangzhou 511466,China;China Railway Economic Planning and Research Institute,Beijing 100038,China)

机构地区:[1]中铁隧道局集团有限公司,广州511466 [2]中国铁路经济规划研究院有限公司,北京100038

出  处:《铁路工程技术与经济》2024年第6期47-52,64,共7页Railway Engineering Technology and Economy

摘  要:铁路隧道竖井施工工序繁琐、工期较长,特别是在竖井井底车场及竖井正洞施工过程中,各种施工设备需要在地面拆解并分块下放至井底,经组装测试后方可正常使用,现行铁路造价标准体系中缺少相应定额或计取标准,本文以大瑞铁路高黎贡山隧道竖井为依托,采用写实记录法测定了竖井施工设备拆解、下放、组装的工料机消耗,并对测定成果合理性进行分析研究,为编制相应补充定额,完善造价标准体系,合理确定工程造价和有效控制投资积累基础数据。The construction process of railway tunnel shaft is cumbersome and the construction period is long,especially in the construction process of the shaft bottom yard and the main shaft.Various construction equipment needs to be disassembled and placed in blocks on the ground to the bottom of the shaft,and can only be used normally after assembly and testing.The current railway cost standard system lacks corresponding quotas or calculation standards.This article takes the Gaoligongshan Tunnel shaft of the Darui Railway as a basis,The consumption of labor,materials,and machinery for dismantling,lowering,and assembling vertical shaft construction equipment was measured using the realistic recording method,and the rationality of the measurement results was analyzed and studied to accumulate basic data for preparing corresponding supplementary quotas,improving the cost standard system,reasonably determining engineering costs,and effectively controlling investment.

关 键 词:隧道 竖井 施工设备 拆解 下放 组装 定额 单价 

分 类 号:U455.1[建筑科学—桥梁与隧道工程]

 