既有地铁车站缺陷侧墙整体置换施工技术研究  

Research on Integral Replacement Construction Technology of Defective Side Wall in Existing Subway Station

在线阅读下载全文

作  者:朱帆 ZHU Fan(China Railway 22nd Bureau Group Rail Engineering Co.,Ltd.,Beijing 100040,China)

机构地区:[1]中铁二十二局集团轨道工程有限公司,北京100040

出  处:《工程技术研究》2025年第3期60-62,共3页Engineering and Technological Research

摘  要:文章以青岛地铁1号线青岛站为研究对象,重点探索了既有地铁车站新型缺陷侧墙整体置换施工技术。该站右线站台层16轴~20轴侧墙出现了混凝土酥松脱落、钢筋锈蚀及结构向内倾斜侵限等严重缺陷。文章通过采取临时支撑加固、缺陷侧墙背后土体膜袋注浆加固、剔除缺陷墙体混凝土后墙内竖支撑及墙后土体开挖支护等技术措施,对该车站侧墙进行了整体置换修复。该技术的应用不仅成功解决了车站的缺陷问题,还为后续地下建筑修复提供了参考和借鉴。Taking Qingdao Station of Qingdao Metro Line 1 as the research object,this paper focuses on the integral replacement construction technology of the new defective side wall in the existing subway station.There are serious defects such as concrete loose shedding,steel corrosion and inward inclination of the structure in the axis 16-axis 20 side wall at the platform floor of the right line of the station.This paper carries out the integral replacement and repair of the side wall of the station by taking technical measures such as temporary support reinforcement,soil membrane bag grouting reinforcement behind the defective side wall,vertical support in the wall after removing the defective wall concrete and excavation and support of the soil behind the wall.The application of this technology not only successfully solves the defect problem of the station,but also provides a reference for the subsequent repair of underground buildings.

关 键 词:既有地铁车站 缺陷墙体 综合注浆加固 临时支撑 监控量测 

分 类 号:U231.4[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象