作 者:王霆[1,2] 刘维宁[1] 罗富荣[2] 李兴高[1]
机构地区:[1]北京交通大学,北京100044 [2]北京市轨道交通建设管理有限公司,北京100037
出 处:《都市快轨交通》2009年第6期81-85,共5页Urban Rapid Rail Transit
基 金:北京市科技计划重点资助项目(D0604003040421)
摘 要:通过大量现场监控量测数据的统计分析,研究在北京地区黏性土与砂性土互层的地质条件下地铁区间隧道浅埋暗挖法施工引起地表沉降的一般特征。结果表明:对于所考虑的17个北京地铁区间工点的现场监测数据,约有95.3%的最大地表沉降小于40mm,大于某沉降值的累计发生频率曲线符合正态分布;地表沉降槽宽度参数的取值范围为0.26~0.60;地铁区间隧道施工引起的地层损失率在0.19%~2%之间。A regression analysis of the field measurements of ground surface settlements induced by bored shallow tunneling in Beijing subway was conducted to acquire empirical estimation of the relevant characteristic parameters. The ground includes silty sand, silty clay, clayey silt, silty time sand, medium and coarse sand, cobble and gravel, which present the typical soil composition in Beijing area. About 95.3% of the maximum surface settlements induced by tunneling were less than 40 mm. The accumulative frequency curve of maximum surface settlement fitted well with the accumulative normal distribution curve. The settlement trough width parameter was 0.26 -0.60. The ground loss ratio was 0.19% -2%. These results are useful for predicting the magnitude and influence range of ground surface settlement.
关 键 词:地铁区间隧道 地表沉降 地表沉降槽宽度参数 地层损失率
分 类 号:U231.3[交通运输工程—道路与铁道工程] U231
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.222